Pagel - Spezial Beton

  • Products
    • evoline
    • Grout
    • Concrete repair
    • Industrial floors and traffic areas
    • Construction products
    • Reaction resins
  • Company
    • Innovations
    • References
    • ISO 9001 & ISO 14001
    • Quality assurance
    • Information
    • Possehl Construction Group
    • Compliance
      • Code of Conduct
      • Supplier Code of Conduct
      • Policy Statement on the Human Rights Strategy
  • Sales
  • English
    • German
    • French
    • Polish
    • Danish
    • Spanish
    • Russian

PAGEL / References

Information about our products

We offer you an extensive range of innovative and high-quality products. In addition to products for standard applications, we also offer a wide range of products for special applications.

Grout
Grout
Concrete repair
Concrete repair
Reaction resins
Reaction resins

Repairs possible for the next 40 years?

Wilhelm-Kaisen-Brücke at Bremen

As part of the renovation of the Wilhelm Kaisen Bridge in Bremen, we are contributing to a clearly defined goal: after renovation, the bridge should have a remaining service life of around 40 years. A key component in this is 16 anchor blocks that integrate the anchor construction in a force-fit manner. It is precisely at this interface that it is decided whether loads are permanently and safely transferred into the construction.
We used V1/160 PAGEL-VERGUSS for the grouting work. A total of approx. 65 tonnes of material was processed in a continuous operation. This placed high demands on logistics, time slots and process stability: conveyor distances of up to 40 metres, very confined spaces and a high degree of reinforcement left little room for improvisation. In addition, grouting heights of up to 1.15 metres had to be achieved – a dimension at which flowability, deaeration and controlled processing must work together consistently.
In order to ensure successful execution from the outset, we produced and evaluated a large-format test specimen in advance under real construction site conditions. This enabled us to test the material behaviour, installation and compaction strategy, and handling on the planned conveyor routes in a practical manner. The findings from this test were directly incorporated into the work preparation and process planning on site.

Ausführende Firmen:

  • PAGEL Technische Mörtel GmbH & Co. KG
  • Baumaschinen Beckschulte KG

Projektort:

  • Wilhelm-Kaisen-Brücke Bremen

Projektziel:

  • Instandsetzung für die nächsten 40 Jahren

Material:

  • V1/160 PAGEL-VERGUSS
  • 65 Tonnen

Ausführungsdauer:

  • 12 Stunden (07.11.2025)

The work was carried out by PAGEL Technische Mörtel und Baumaschinen Beckschulte KG. The key factors were a steady, continuous supply of material and a well-timed installation process, so that the grouting could be carried out without interruptions and without compromising on quality.

Concrete pouring underwater?

Harbour basin renovation in Mühlheim

From analysis to execution: systematic harbour repair

This repair project in the harbour basin focused on one thing: protecting existing structures rather than replacing them. During ongoing harbour operations, downtime is expensive, access is restricted and boundary conditions are challenging. This is precisely where a solution that is technically safe, economical and reliable is needed.
We at PAGEL Spezial-Beton & PAGEL Technische Mörtel have been involved in the harbour basin renovation from the very beginning – from preliminary tests to ensure the suitability of materials and processes, to helping design the installation technology, to the final grouting. The goal was to achieve a permanent repair of the harbour structure

https://www.pagel.com/all/images/Referenzen/Mulheim%201.mp4

Ausführende Firmen:

  • PAGEL Technische Mörtel GmbH & Co. KG

Projektort:

  • Mühlheimer Hafen

Projektziel:

  • Sanierung der Fehlstellen im Hafenbecken

Material:

  • PAGEL V80C45 Vergussbeton

Ausführungsdatum

  • 23.01.2026

Underwater grouting: industrial divers, formwork and controlled insertion

The special feature: grouting and concreting work underwater. Industrial divers were employed in the construction to precisely formwork the defective areas. Underwater, they professionally switch on the areas, thus creating the basis for a dense, dimensionally stable grouting space.
In addition, the divers installed a filling pipe through which the grout could be introduced in a controlled manner underwater. This allowed the material to be guided precisely, preventing segregation and ensuring the quality of the application even under difficult visibility and flow conditions.

Casting from the pulling platform

Material feed, timing and insertion technology were optimised for the work from the train platform. PAGEL V80C45 was used as the grouting material – an ideal solution for demanding conditions where workability, stability and process reliability are crucial.

Economical renovation – preserving substance

Targeted repair of defects in the harbour basin saved time, money and resources. The result: predictable, reliable concrete repair with high-quality workmanship, even underwater and during ongoing operations.

  • LinkedIn
  • Facebook
  • Instagram
  • YouTube
  • Products
    • evoline
    • Grout
    • Concrete repair
    • Industrial floors and traffic areas
    • Construction products
    • Reaction resins
  • PAGEL Spezial-Beton
    • Innovations
    • References
    • Quality assurance
    • Information
    • Site notice
    • Privacy policy
    • Contact
Possehl Construction Group
  • Products
  • PAGEL Spezial-Beton

Copyright © 2026 · Minimum Pro on Genesis Framework · WordPress · Log in